| List of Contents |
|
| File ID |
Filing Date |
Document Title |
Pages |
Photo |
|
| 407080 |
Dec 05, 2008 | Log of availble digital files via DVD |
3 | |
| 405678 |
Nov 17, 2008 | Finite Element Analysis simulation of failure intitation mechanism from Board presentation |
-- | |
| 407688 |
Dec 15, 2008 | Video File - Initial Failure Animation |
-- | |
| 407687 |
Dec 15, 2008 | Video File - Structure and Components animation |
-- | |
| 407686 |
Dec 15, 2008 | Video File Animation descriptions and disclaimer |
2 | |
| 405006 |
Nov 05, 2008 | Witness and Victim Interviews |
413 | |
| 375411 |
Aug 17, 2007 | Photo 1. Overhead view of bridge in water looking north |
| 1 |
| 387871 |
Mar 13, 2008 | State-by-state bridge counts |
6 | |
| 383930 |
Jan 14, 2008 | FHWA Interim Report - Adequacy of the U10 & L11 Gusset Plate Designs for the Minnesota Bridge No. 9340 (I-35W over the Mississippi River) |
20 | |
| 404084 |
Oct 24, 2008 | FHWA Final Report on Gusset Plate Design Adequacy |
20 | |
| 383947 |
Jan 14, 2008 | Bridge Diagram showing locatons of gussets U10 & L11 |
1 | |
| 387406 |
Mar 07, 2008 | Photos of I-35W bridge |
26 | |
| 379683 |
Oct 29, 2007 | Truss Diagram Nomenclature and Salvage Log |
37 | |
| 386200 |
Feb 21, 2008 | Materials Lab - Factual Report 07-119 Gusset Plate |
4 | |
| 391041 |
Apr 18, 2008 | Materials Lab - Factual Report 08-004 L10-L11W |
12 | |
| 386487 |
Feb 26, 2008 | Materials laboratory factual report 08-006 Hardness measurements |
3 | |
| 404965 |
Nov 05, 2008 | Materials Laboratory Factual Report 08-096, Laser scans and corrosion measurements of L11 gusset plates |
63 | |
| 387408 |
Mar 07, 2008 | Structural Investigation Group Chairman Factual Report 08-015 (Materials Lab) |
135 | |
| 387407 |
Mar 07, 2008 | Modeling Group Contractor Interim Report |
40 | |
| 405446 |
Nov 12, 2008 | Modeling Group Chairman Final Report 08-119 |
271 | |
| 385259 |
Feb 07, 2008 | Modeling Group Study 07-115, Loads on the bridge at the time of the accident |
26 | |
| 404087 |
Oct 24, 2008 | FHWA I35W TFHRC Model Report Final |
138 | |
| 404944 |
Nov 05, 2008 | Modeling Group Study Report 07-115B, Erratum - correction to Table 4 |
2 | |
| 403416 |
Oct 17, 2008 | BSDI I-35W Review of Original Design |
69 | |
| 404089 |
Oct 24, 2008 | FHWA Materials Property Testing Report |
61 | |
| 400050 |
Aug 25, 2008 | Materials Laboratory Study Report 08-086, Truss Loads during Construction and Change in Angle |
23 | |
| 405240 |
Nov 07, 2008 | Materials Laboratory Study Report 08-103, Chord splice calculations for preliminary and final designs of I-35W bridge |
52 | |
| 405373 |
Nov 11, 2008 | BridgeU10W_bow0_Riks_U3_Animation |
-- | |
| 405374 |
Nov 11, 2008 | BridgeU10W_meshP2_Riks_MisesStress_Animation |
-- | |
| 405375 |
Nov 11, 2008 | BridgeU10W_meshP5_Riks_MisesStress_Animation |
-- | |
| 405242 |
Nov 07, 2008 | Materials Laboratory Study Report 08-117, Review of Sverdrup manual and Orinoco bridge computations |
16 | |
| 405239 |
Nov 07, 2008 | Materials Laboratory Study Report 08-118, Calculation of differential temperature for I-35W bridge |
37 | |
| 399813 |
Aug 21, 2008 | Materials Lab - Factual Report 08-073 Erection Sequence |
14 | |
| 398902 |
Aug 07, 2008 | Materials Laboratory Study 08-062, Comparison of Gusset Plate Design Characteristics |
16 | |
| 391631 |
Apr 29, 2008 | Materials Lab - Factual Report 08-031 nodes L11 |
9 | |
| 392371 |
May 07, 2008 | Materials Lab - Factual Report 08-053 Gusset plate hardness |
3 | |
| 394629 |
Jun 05, 2008 | Digital Video Recording Images |
1 | |
| 401355 |
Sep 12, 2008 | Specialist's Study Report Gusset Plate Photograph Measurements |
38 | |
| 394730 |
Jun 06, 2008 | Pre-Collapse Images - Nodes U10 and L11 |
21 | |
| 394892 |
Jun 10, 2008 | Video Study |
54 | |
| 403418 |
Oct 17, 2008 | Materials Lab - Collapse Sequencing Study Photos 08-032A |
29 | |
| 403417 |
Oct 17, 2008 | Materials Lab - Collapse Sequencing Study 08-032 |
28 | |
| 401312 |
Sep 11, 2008 | Materials Lab - Study 08-074 Design |
13 | |
| 405224 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference A |
21 | |
| 405237 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference B |
32 | |
| 405225 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference C |
26 | |
| 405226 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference D |
4 | |
| 405227 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference E |
3 | |
| 405228 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference F |
3 | |
| 405229 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference G |
10 | |
| 405230 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference H |
3 | |
| 405231 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference I |
1 | |
| 405232 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference J |
2 | |
| 405233 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference K |
2 | |
| 405234 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference L |
5 | |
| 405235 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference M |
2 | |
| 405467 |
Nov 12, 2008 | Materials Lab - Factual Report 08-074 Referencec N and O |
1 | |
| 405236 |
Nov 07, 2008 | Materials Lab - Factual Report 08-074 Reference P |
22 | |
| 406197 |
Nov 21, 2008 | Design drawings and shop drawings used to create U10 and L11 finite element models |
30 | |
| 396800 |
Jul 09, 2008 | Witness Group Chairman Factual Report |
7 | |
| 396802 |
Jul 09, 2008 | Witness Group Chairman Factual Report - Attachment A: Spreadsheet of Contacts |
11 | |
| 398231 |
Jul 29, 2008 | Witness Group Chairman Factual Report - Attachment B: Summaries of Witness Interviews |
151 | |
| 396806 |
Jul 09, 2008 | Witness Group Chairman Factual Report - Attachment C: Summaries of Other Information Interviews |
46 | |
| 397147 |
Jul 15, 2008 | Survival Factors - Group Chairman Factual Report |
12 | |
| 400746 |
Sep 04, 2008 | Survival Factors - Attachment 1, Vehicle Information |
5 | |
| 397150 |
Jul 15, 2008 | Survival Factors - Attachment 2, Interviews |
28 | |
| 397155 |
Jul 15, 2008 | Survival Factors Attachment-A, HCSO Dispatch Logs |
14 | |
| 397156 |
Jul 15, 2008 | Survival Factors Attachment-B, HCSO Dive Operations Report |
6 | |
| 397157 |
Jul 15, 2008 | Survival Factors Attachment-C, Minneapolis FD Dispatch Logs |
33 | |
| 397250 |
Jul 16, 2008 | Survival Factors Attachment-D, Minneapolis FD Field Report |
28 | |
| 397251 |
Jul 16, 2008 | Survival Factors Attachment-E, Minneapolis PD Dispatch Logs |
60 | |
| 397252 |
Jul 16, 2008 | Survival Factors Attachment-F, USACE Mississippi River Navigation Bulletins |
4 | |
| 397253 |
Jul 16, 2008 | Survival Factors Attachment-G, Hennepin County EOC Debriefing |
6 | |
| 404391 |
Oct 28, 2008 | Factual Report of Sverdrup & Parcell Engineering Employees Interviewed |
12 | |
| 405128 |
Nov 06, 2008 | Highway Construction Factors Factual Report |
45 | |
| 398327 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 1 - Interview Transcript of MnDOT Bridge Inspector Harvey Unruh |
18 | |
| 398329 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 2 - Weight Tickets for Material Loads on the Bridge at the Time of the Collapse |
9 | |
| 398330 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 3 - Diagrams for Overlays |
9 | |
| 398331 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 4 - Excerpts from Construction Project Design Plans |
17 | |
| 398340 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 5 - Excerpts from the Construction Contract (S-29) |
2 | |
| 398341 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 6 - Pre-Construction Conference Minutes |
7 | |
| 398471 |
Jul 31, 2008 | Highway Construction Factors Group Attachment 7A - MnDOT Weekly Construction Diaries |
31 | |
| 398472 |
Jul 31, 2008 | Highway Construction Factors Group Attachment 7B - MnDOT Weekly Construction Diaries |
29 | |
| 398475 |
Jul 31, 2008 | Highway Construction Factors Group Attachment 7C - MnDOT Weekly Construction Diaries |
38 | |
| 398478 |
Jul 31, 2008 | Highway Construction Factors Group Attacment 7D - MnDOT Weekly Construction Diaries |
25 | |
| 398479 |
Jul 31, 2008 | Highway Construction Factors Group Attachment 7E - MnDOT Weekly Construction Diaries |
24 | |
| 398343 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 8 - Overweight Permits Issued |
112 | |
| 398344 |
Jul 30, 2008 | Highway Construction Factor Group Attachment 8B - Overweight Permits Issued |
33 | |
| 398345 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 8C - Overweight Permits Issued |
17 | |
| 398347 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 8D - Overweight Permits Issued |
22 | |
| 398348 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 8E - Overweight Permits Issued |
18 | |
| 398350 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 9 - Critical Path Method (CPM) Schedule |
10 | |
| 398353 |
Jul 30, 2008 | Highway Construction Factors Group Attachment 10 - Minutes of Weekly Meetings by MnDOT Project Engineer |
11 | |
| 405357 |
Nov 11, 2008 | Highway Construction Factors Group Attachment 11, Ramsey County Sheriff's Office Interview Summaries of PCI Work Crew |
46 | |
| 405082 |
Nov 06, 2008 | Highway Construction Factors Group Attacment 12 - Policies Restriction Construction Loads on Bridge Decks1. MNDOT Construction Specification 1513 (old Version in effect at time of collapse2. FHWA Technical Advisory 5140.283. AASHTO Policy 8.15.3 |
6 | |
| 405086 |
Nov 06, 2008 | Highway Construction Factors Group Attachment 13 - List of Fire Department Apparatus Using Bridge 9340 |
3 | |
| 405087 |
Nov 06, 2008 | Highway Construction Factors Group Attachment 14 - 1977 Overlay Inspection Report From Bridge 9340 |
13 | |
| 405089 |
Nov 06, 2008 | Highway Construction Factors Group Attachment 15 - AASHTO POLL on Brige Design Peer Reviews and Construction Loading Policy Restrictions |
2 | |
| 405097 |
Nov 06, 2008 | Highway Construction Factors Group Attachment 16 - MNDOT Revisions to Construction Specification 1513, "Restrictions on Movement and Storage of Heavy Loads and Equipment"Dated 4/08/2008 and 9/18/2008 |
3 | |
| 405106 |
Nov 06, 2008 | Highway Construction Factors Group Attachment 17 - State Bridge Loading Restrictions During Construction for Alabama, California, Massachusetts, and Minnesota |
43 | |
| 405107 |
Nov 06, 2008 | Highway Construction Factors GroupAttachment 18 Part ANew York Specifications for Restricting Bridge Loading During Construction |
61 | |
| 405111 |
Nov 06, 2008 | Highway Construction Factors Group attachment 18 Part BNew York Specifications Continued |
70 | |
| 405127 |
Nov 06, 2008 | Highway Construction Factors Group Attachment 19 State Policies Restriction Construction loading on Bridges in Ohio, Oregon, Texas, Washington, West Virginia, and Pennsylvania |
82 | |
| 405135 |
Nov 06, 2008 | Photograph of Aggregates on Bridge Deck |
| 1 |
| 404013 |
Oct 23, 2008 | Bridge Design Group - Bridge Design Group Chairman Factual Report |
89 | |
| 401899 |
Sep 20, 2008 | Bridge Design Group - Addendum to Bridge Design Group Chairman Factual Report |
72 | |
| 404908 |
Nov 04, 2008 | Bridge Design Group - Attachment 1, National Bridge Inventory (NBI) forms for the I-35W Bridge (Bridge #9340) from 1983 through 2007 |
76 | |
| 401903 |
Sep 20, 2008 | Bridge Design Group - Attachment 2, Letter to the National Transportation Safety Board from the Minnesota Department of Transportation dated April 22, 2008 |
3 | |
| 401905 |
Sep 20, 2008 | Bridge Design Group - Attachment 3, Minnesota Department of Transportation Bridge Inspection Manual dated May 2007 |
78 | |
| 401907 |
Sep 20, 2008 | Bridge Design Group - Attachment 4, Mn/DOT Bridge Inspection Reports dated August 5, 1990 and October 18, 1993 |
10 | |
| 401909 |
Sep 20, 2008 | Bridge Design Group - Attachment 5, Mn/DOT Fracture Critical Bridge Inspection In-Depth Report dated June 2006 |
51 | |
| 401911 |
Sep 20, 2008 | Bridge Design Group - Attachment 6, Letter to the National Transportation Safety Board from the Minnesota Department of Transportation dated December 19, 2007 |
16 | |
| 401912 |
Sep 20, 2008 | Bridge Design Group - Attachment 7, FHWA's Apportionment Process for Highway Bridge Program (HBP) Funds |
9 | |
| 401914 |
Sep 20, 2008 | Bridge Design Group - Attachment 8, Mn/DOT Fracture Critical Bridge Inspection Annual Report dated June 2004 |
47 | |
| 401916 |
Sep 20, 2008 | Bridge Design Group - Attachment 9, Letter to the National Transportation Safety Board from the Minnesota Department of Transportation dated September 21, 2007 |
40 | |
| 401917 |
Sep 20, 2008 | Bridge Design Group - Attachment 10, Mn/DOT Bridge Inspection Report dated June 15, 2006 |
5 | |
| 401919 |
Sep 20, 2008 | Bridge Design Group - Attachment 11, Mn/DOT Guidelines for In-Depth Inspection of Failure Critical and Other Non-Redundant Bridges and for Underwater Inspections dated July 19, 2007 |
7 | |
| 401921 |
Sep 20, 2008 | Bridge Design Group - Attachment 12, Mn/DOT Technical Memorandum regarding "Critical Deficiencies" found during bridge inspections dated July 20, 2005 |
6 | |
| 401922 |
Sep 20, 2008 | Bridge Design Group - Attachment 13, URS Corporation Fatigue Evaluation and Redundancy Analysis Draft Report for Bridge #9340, Executive Summary, dated January 2007 |
5 | |
| 402209 |
Sep 24, 2008 | Bridge Design Group – Attachment 14, URS Corporation Fatigue Evaluation Redundancy Analysis Draft Report for Bridge #9340 dated July 2006 |
300 | |
| 401923 |
Sep 20, 2008 | Bridge Design Group - Attachment 15, URS Corporation Fatigue Evaluation Bridge 9340 35W over Mississippi River Second Inspection Report dated November 17, 2003 |
30 | |
| 402211 |
Sep 24, 2008 | Bridge Design Group – Attachment 16, URS Corporation Fatigue Evaluation Bridge 9340 35W over Mississippi River Initial Inspection Report dated June 9, 2003 |
100 | |
| 401924 |
Sep 20, 2008 | Bridge Design Group - Attachment 17, University of Minnesota Fatigue Evaluation of the Deck Truss of Bridge 9340 Final Report dated March 2001 |
90 | |
| 401927 |
Sep 21, 2008 | Bridge Design Group - Attachment 18, Mn/DOT Memorandums documenting cracks in the north approach span girder near Pier 9 from October 1998 through November 2000 |
21 | |
| 401929 |
Sep 21, 2008 | Bridge Design Group - Attachment 19, Ayres Associates Underwater Bridge Inspection Report for Bridge #9340 dated December 8, 2004 |
10 | |
| 401931 |
Sep 21, 2008 | Bridge Design Group - Attachment 20, Email to the National Transportation Safety Board from the Minnesota Department of Transportation dated January 10, 2008 |
3 | |
| 401932 |
Sep 21, 2008 | Bridge Design Group - Attachment 21, Mn/DOT LRFD Bridge Design Manual, Chapter 15 Bridge Rating, dated June 2007 Draft |
15 | |
| 401934 |
Sep 21, 2008 | Bridge Design Group - Attachment 22, Mn/DOT Bridge Rating and Load Posting Report dated December 14, 1995 |
7 | |
| 401936 |
Sep 21, 2008 | Bridge Design Group - Attachment 23, Letter to the National Transportation Safety Board from the Minnesota Department of Transportation dated January 8, 2008 |
43 | |
| 401937 |
Sep 21, 2008 | Bridge Design Group - Attachment 24, Mn/DOT BARS load rating computer printout dated December 11, 1995 |
63 | |
| 401938 |
Sep 21, 2008 | Bridge Design Group - Attachment 25, Mn/DOT BARS load rating computer printout dated August 18, 1997 |
95 | |
| 401940 |
Sep 21, 2008 | Bridge Design Group - Attachment 26, Email to the National Transportation Safety Board from the Minnesota Department of Transportation dated November 2, 2007 |
3 | |
| 401942 |
Sep 21, 2008 | Bridge Design Group - Attachment 27, Mn/DOT Bridge Rating and Load Posting Report dated September 17, 1979 |
2 | |
| 401944 |
Sep 21, 2008 | Bridge Design Group - Attachment 28, Email to the National Transportation Safety Board from the Minnesota Department of Transportation dated October 10, 2007 |
2 | |
| 401945 |
Sep 21, 2008 | Bridge Design Group - Attachment 29, FHWA Turner-Fairbank Highway Research Center Report Assessment of the Load Rating Records for Minnesota Bridge No. 9340 (I-35W over the Mississippi River) dated June 30, 2008 |
10 | |
| 401947 |
Sep 21, 2008 | Bridge Design Group - Attachment 30, Email to the Minnesota Department of Transportation from the National Transportation Safety Board dated October 15, 2007 |
2 | |
| 401948 |
Sep 21, 2008 | Bridge Design Group - Attachment 31, Mn/DOT transmittal of report to NTSB entitled Load Rating of Bridge 9340 with Construction Loads |
4 | |
| 401950 |
Sep 21, 2008 | Bridge Design Group - Attachment 32, Copy of minutes of meetings, emails, and handwritten notes from July 24, 2006 through May 2007 as it relates to proposal for steel plating of all 52 fracture critical truss members |
68 | |
| 401952 |
Sep 21, 2008 | Bridge Design Group - Attachment 33, Field notes taken by Mn/DOT Inspection Team dated May 2007 |
16 | |
| 401953 |
Sep 21, 2008 | Bridge Design Group - Attachment 34, Mn/DOT correspondence and photographs of washout hole between Pier 4 and 5 |
7 | |
| 401954 |
Sep 21, 2008 | Bridge Design Group - Attachment 35, Mn/DOT concrete core testing of bridge deck dated August 23, 2007 |
3 | |
| 401956 |
Sep 21, 2008 | Bridge Design Group - Attachment 36, Minnesota Classification Questionnaire dated February 24, 1960 |
6 | |
| 401957 |
Sep 21, 2008 | Bridge Design Group - Attachment 37, Minnesota Highway Department Bridge Design Manual dated April 12, 1972 |
3 | |
| 401959 |
Sep 21, 2008 | Bridge Design Group - Attachment 38, Consultant agreement between Mn/DOT and Sverdrup and Parcel and Associates, Inc. dated November 5, 1962 |
22 | |
| 401960 |
Sep 21, 2008 | Bridge Design Group - Attachment 39, Mn/DOT consultant services work type definition dated March 26, 2003 |
8 | |
| 401962 |
Sep 21, 2008 | Bridge Design Group - Attachment 40, Letter to the National Transportation Safety Board from the Minnesota Department of Transportation dated March 6, 2008 |
3 | |
| 401964 |
Sep 21, 2008 | Bridge Design Group - Attachment 41, Letter to the National Transportation Safety Board from the Minnesota Department of Transportation dated March 24, 2008 |
3 | |
| 401986 |
Sep 22, 2008 | Bridge Design Group - Attachment 42, Mn/DOT Load and Resistance Factor Design (LRFD) Bridge Design Manual |
6 | |
| 401993 |
Sep 22, 2008 | Bridge Design Group - Attachment 43, Email to the National Transportation Safety Board from the Federal Highway Administration - Minnesota Division Office dated March 7, 2008 |
3 | |
| 401994 |
Sep 22, 2008 | Bridge Design Group - Attachment 44, FHWA Memorandum to Division Administrators dated February 22, 2007 |
5 | |
| 401995 |
Sep 22, 2008 | Bridge Design Group - Attachment 45, FHWA Bridge Program Manual dated August 2004 |
19 | |
| 402042 |
Sep 22, 2008 | Bridge Design Group - Attachment 46, Sverdrup & Parcel and Associates, Inc. document entitled Procedure for Checking Design Notes and Coordinating Same with Detail Checker dated September 1953 |
3 | |
| 402044 |
Sep 22, 2008 | Bridge Design Group - Attachment 47, Sverdrup & Parcel and Associates, Inc. document entitled Quality Control Coordination and Checking Procedures dated April 1975 |
20 | |
| 402045 |
Sep 22, 2008 | Bridge Design Group - Attachment 48, Answers to standard set of questions by the California DOT (Caltrans) |
15 | |
| 402183 |
Sep 23, 2008 | Bridge Design Group - Attachment 49, Answers to standard set of questions by the Florida DOT |
4 | |
| 402184 |
Sep 23, 2008 | Bridge Design Group - Attachment 50, Answers to standard set of questions by the Iowa DOT |
22 | |
| 404724 |
Nov 01, 2008 | Bridge Design Group - Attachment 51, Answers to standard set of questions by the Kansas DOT |
22 | |
| 402186 |
Sep 23, 2008 | Bridge Design Group - Attachment 52, Answers to standard set of questions by the Maryland State Highway Administration |
4 | |
| 402188 |
Sep 23, 2008 | Bridge Design Group - Attachment 53, Answers to standard set of questions by the Minnesota DOT |
65 | |
| 402189 |
Sep 23, 2008 | Bridge Design Group - Attachment 54, Answers to standard set of questions by the Nebraska Department of Roads |
3 | |
| 402190 |
Sep 23, 2008 | Bridge Design Group - Attachment 55, Answers to standard set of questions by the New York State DOT |
33 | |
| 402194 |
Sep 24, 2008 | Bridge Design Group - Attachment 56, Answers to standard set of questions by the Ohio DOT |
3 | |
| 402195 |
Sep 24, 2008 | Bridge Design Group - Attachment 57, Answers to standard set of questions by the Oregon DOT |
3 | |
| 402197 |
Sep 24, 2008 | Bridge Design Group - Attachment 58, Answers to standard set of questions by the Pennsylvania DOT |
41 | |
| 402198 |
Sep 24, 2008 | Bridge Design Group - Attachment 59, Answers to standard set of questions by the Tennessee DOT |
3 | |
| 402199 |
Sep 24, 2008 | Bridge Design Group - Attachment 60, Answers to standard set of questions by the Texas DOT |
35 | |
| 402200 |
Sep 24, 2008 | Bridge Design Group - Attachment 61, Answers to standard set of questions by the Virginia DOT |
65 | |
| 402202 |
Sep 24, 2008 | Bridge Design Group - Attachment 62, Answers to standard set of questions by the Washington State DOT |
3 | |
| 405475 |
Nov 12, 2008 | NTSB Interviews of MnDOT Inspectors |
63 | |
| 404915 |
Nov 04, 2008 | Factual Summary of State DOT Responses to Bridge Design Errors |
9 | |
| 404911 |
Nov 04, 2008 | Factual Summary of Findings from Other Bridges in the Minnesota DOT Inventory |
6 | |
| 404914 |
Nov 04, 2008 | Factual Report of Corroded Gusset Plates on Ohio Bridges |
8 | |
| 404912 |
Nov 04, 2008 | Federal Highway Administration Bridge Inspection Training Specific to Gusset Plates |
10 | |
| 405222 |
Nov 07, 2008 | Factual Summary of Employee Interviews |
7 | |
| 404913 |
Nov 04, 2008 | Factual Summary of Interviews with Former Sverdrup & Parcel Employees: T. Dillon and W. Gaddis |
3 | |
| 404827 |
Nov 03, 2008 | Gray, Plant, Mooty - Investigative Report to Joint Committee to Investigate the I-35W Bridge Collapse, Dated May 2008 |
126 | |
| 404995 |
Nov 05, 2008 | Wiss, Janney, Elstner Associates, Inc. - I-35W Bridge over the Mississippi River: Collapse Investigation, Final Report, November 2008 |
176 | |
| 404829 |
Nov 03, 2008 | Submission of Progressive Contractors, Inc. to the National Transportation Safety Board, October 2008 |
16 | |
| 404830 |
Nov 03, 2008 | Mn/DOT response to PCI Submission, Dated October 20, 2008 |
1 | |
| 405358 |
Nov 11, 2008 | Submission of Jacobs Engineering Group, Inc. to the National Transportation Safety Board, November 2008 |
7 | |
| 405476 |
Nov 12, 2008 | Mn/DOT response to Jacobs Engineering Submission, Dated November 12, 2008 |
1 | |
| 405150 |
Nov 06, 2008 | Sandia National Laboratories Peer Review of the National Transportation Safety Board Structural Analysis of the I-35W Bridge Collapse, October 2008 |
14 | |
| 405359 |
Nov 11, 2008 | Presentation 01 - Photo of post-collapse dive operations (source FHWA) |
| 1 |
| 405360 |
Nov 11, 2008 | Presentation 02 - Photo of debris removal (source FHWA) |
| 1 |
| 405361 |
Nov 11, 2008 | Presentation 03 - photo of debris removal (source FHWA) |
| 1 |
| 405362 |
Nov 11, 2008 | Presentation 04 - Photo of debris removal (source FHWA) |
| 1 |
| 405363 |
Nov 11, 2008 | Presentation 05 - Photo of post-collapse vehicles (source MPD) |
| 1 |
| 405364 |
Nov 11, 2008 | Presentation 06 - Photo of post-collapse vehicles (source MPD) |
| 1 |
| 405365 |
Nov 11, 2008 | Presentation 07 - Photo of post-collapse vehicles (source MPD) |
| 1 |
| 405366 |
Nov 11, 2008 | Presentation 08 - Photo of post-collapse rescue efforts (source MPD) |
| 1 |
| 405367 |
Nov 11, 2008 | Presentation 09 - Photo of post-collapse rescue efforts (source MPD) |
| 1 |
| 405368 |
Nov 11, 2008 | Presentation 10 - Photo of post-collapse rescue efforts (source MPD) |
| 1 |
| 405369 |
Nov 11, 2008 | Presentation 11 - Photo of post-collapse rescue efforts (source MPD) |
| 1 |