Synopsis: ABOUT 3:25 P.M. A 1988 MACK TRUCK WITH A CONCRETE MIXER BODY WAS UNABLE TO STOP AS IT APPROACHED A "T" INTERSECTION AT THE BOTTOM OF AN EXIT RAMP IN PLYMOUTH MEETING, PENNSYLVANIA. AS THE TRUCK PROCEEDED THROUGH THE INTERSECTION, IT COLLIDED WITH & OVERRODE A 1985 SUBARU PASSENGER CAR. THE SUBARU DRIVER WAS KILLED; THE TRUCKDRIVER SUSTAINED MINOR INJURIES. THE TRUCKDRIVER WAS UNRESTRAINED; THE SUBARU DRIVER WAS FOUND RESTRAINED IN HER VEHICLE. THE WEATHER WAS CLEAR & DRY. NO FIRE ENSUED, & NO OTHER VEHICLE OCCUPANTS WERE INVOLVED IN THE ACCIDENT.
Recommendation: THE NTSB RECOMMENDS THAT THE JDM MATERIALS COMPANY, INC.: IMPLEMENT PROCEDURES THAT WILL ENSURE THAT AIR BRAKE MANUFACTURERS' SUGGESTED INSTALLATION, INSPECTION, & FUNCTIONAL TEST PROCEDURES ARE ADHERED TO BY COMPANY MECHANICS PERFORMING MAINTENANCE ON THE COMPANY'S TRUCK BRAKE SYSTEMS.
Original recommendation transmittal letter: PDF
Overall Status: Closed - Acceptable Action
Mode: Highway
Location: Plymouth Meeting, PA, United States
Is Reiterated: No
Is Hazmat: No
Is NPRM: No
Accident #: NRH96FH009
Accident Reports: Truck Loss of Braking Contol on Steep Downgrade and Collision with a Vehicle
Report #: HAR-97-02-SUM
Accident Date: 4/25/1996
Issue Date: 10/29/1997
Date Closed: 5/25/2001
Addressee(s) and Addressee Status: JDM Materials Company, Inc. (Closed - Acceptable Action)
Keyword(s):

Safety Recommendation History
From: NTSB
To: JDM Materials Company, Inc.
Date: 5/25/2001
Response: The Safety Board notes that JDM instituted several safety procedures, including a prompt post-accident inspection of the entire fleet, following the accident. Additionally, as a result of your discussions with Mr. O’Neill of our staff, JDM mechanics are now required to adhere to air brake manufacturers’ procedures when installing, testing, and inspecting company truck brake systems. Based on this information, Safety Recommendation H-97-35 is classified “Closed--Acceptable Action.”

From: JDM Materials Company, Inc.
To: NTSB
Date: 3/19/2001
Response: Letter Mail Controlled 03/26/2001 7:28:09 PM MC# 2010253 As stated in Mr. Hall’s letter, a prompt post accident inspection of the entire fleet was completed to verify the status of all the air brake systems. As a follow up to that inspection, each and every repair that may even remotely affect the air brake systems triggers a complete examination of those systems. If a vehicle has not had any repair, which would trigger an examination, J.D.M. Materials Co. has made an examination of the air brake systems concurrent with the semi-annual Pennsylvania state inspection program.

From: NTSB
To: JDM Materials Company, Inc.
Date: 3/2/2001
Response: The Safety Board has received no reply from your company regarding Safety Recommendation H-97-35. The Board would appreciate learning what action, if any, your company has taken to implement this recommendation. A copy of the original recommendation letter is enclosed. Please refer to Safety Recommendation H-97-35 in your reply, and address your response to Ms. Carol J. Carmody, Acting Chairman.