Synopsis: ABOUT 11:30 A.M., ON NOVEMBER 30, 1988, A TRACTOR-FLATBED SEMITRAILER OPERATED BY HY YIELD BROMINE COMPANY OVERTURNED AT THE INTERSECTION OF TWO FARM ROADS IN A SPARSELY POPULATED AREA OF COLLIER COUNTY, FLORIDA. THE SEMITRAILER WAS LOADED WITH 32 CYLINDERS OF A POISONOUS AND TOXIC BY INHALATION MIXTURE, 98 PERCENT METHYL BROMIDE AND 2 PERCENT CHLOROPICRIN. ELEVEN OF THE CYLINDERS WERE FULL, EACH CONTAINING ABOUT 1,500 POUNDS OF THE POISONOUS MIXTURE, AND THE REMAINDER OF THE CYLINDERS WERE PARTIALLY FULL OR EMPTY EXCEPT FOR RESIDUE. THE DRIVER HAD COMPLETED THE SECOND OF FOUR SCHEDULED STOPS WHEN THE ACCIDENT OCCURRED.
Recommendation: THE NTSB RECOMMENDS THAT THE RESEARCH AND SPECIAL PROGRAMS ADMINISTRATION: AMEND INSPECTION AND TESTING REQUIREMENTS FOR PRESSURE CYLINDERS TO MAKE THE REQUIREMENTS CLEAR AND CONSISTENT.
Original recommendation transmittal letter: PDF
Overall Status: Closed - Acceptable Action
Mode: Intermodal
Location: Collier County, FL, United States
Is Reiterated: No
Is Hazmat: No
Is NPRM: No
Accident #: DCA89MZ001
Accident Reports: ​Puncture of a Cylinder Containing a Mixture of Methyl Bromide and Chloropicrin Following the Overturn of a Tractor/Semitrailer
Report #: HZM-90-01
Accident Date: 11/30/1988
Issue Date: 3/23/1990
Date Closed: 3/16/1998
Addressee(s) and Addressee Status: RSPA (Closed - Acceptable Action)
Keyword(s): Hazmat

Safety Recommendation History
From: NTSB
To: RSPA
Date: 3/16/1998
Response: BECAUSE DOCKET HM-220B, "RESTRUCTURING OF CYLINDER SPECIFICATIONS REQUIREMENTS" CLARIFIED THE PORTIONS OF THE INSPECTION AND TESTING REQUIREMENTS THAT HAD CONCERNED THE SAFETY BOARD, SAFETY RECOMMENDATION I-90-10 IS RECLASSIFIED "CLOSED--ACCEPTABLE ACTION."

From: RSPA
To: NTSB
Date: 11/17/1997
Response: RSPA ISSUED A FINAL RULE UNDER DOCKED HM-220A, TITLED "PERIODIC INSPECTION AND TESTING OF CYLINDERS." THE RULE WAS EFFECTIVE OCTOBER 1, 1996 AND CALRIFIED CERTAIN CURRENT INSPECTION AND RETEST REQUIREMENTS. DOCKET HM-220B TITLED "RESTRUCTURING OF CYLINDER SPECIFICATIONS REQUIREMENTS" ADDRESSED CYLINDER MANUFACTURING AND CLARIFIED PORTIONS OF THE INSPECTION AND TESTING REQUIREMENTS

From: NTSB
To: RSPA
Date: 10/4/1995
Response: THE BOARD IS CONCERNED THAT RSPA HAS NOT FOLLOWED UP ON ITS PRIOR COMMITMENTS & HAS NOT MADE NOTICEABLE PROGRESS ON THE SAFETY ISSUES ADDRESSED BY I-90-8 THROUGH -10 IN MORE THAN 5 YEARS. RSPA INDICATES SUPPORT FOR THESE RECOMMENDATIONS BUT HAS DEMONSTRATED NO SUBSTANTIVE PROGRESS. THEREFORE I-90-8 THROUGH -10 WILL REMAIN CLASSIFIED "OPEN--UNACCEPTABLE RESPONSE."

From: RSPA
To: NTSB
Date: 7/28/1995
Response: A DRAFT NPRM WHICH ADDRESSES THIS RECOMMENDATION IS UNDER DEVELOPMENT & IS PLANNED FOR PUBLICATION BY THE END OF THE YEAR. THEY REQUESTED THAT THE SR BE CLASSIFIED "OPEN--ACCEPTABLE ACTION" PENDING PUBLICATION OF THE NPRM.

From: NTSB
To: RSPA
Date: 7/8/1994
Response: THE BOARD IS CONCERNED THAT AFTER 4 YEARS, RSPA HAS YET TO BEGIN OR IS STILL GATHERING INFO NEEDED TO INITIATE REGULATORY ACTION ON THE SAFETY ISSUES ADDRESSED BY RECOMMENDATIONS I-90-8, 9, & -10. THE BOARD DOES NOT BELIEVE THAT RSPA HAS MADE ANY SUBSTANTIVE PROGRESS TOWARD THE IMPLENTATION OF THESE THREE RECOMMENDATIONS, & WE URGE RSPA TO EXPEDITE ITS EFFORTS TO COMPLETE THE NEEDED REGULATORY ACTION. ALSO REGARDING I-90-10, RSPA INDICATED THAT THE ANPRM WILL FOCUS ON HIGH-PRESSURE CYLINDERS, WHICH MAY NOT INCLUDE SPECIFICATION 4BW CYLINDERS (THOSE INVOLVED IN THE ACCIDENT THAT LED TO THIS RECOMMENDATION). BECAUSE OF THE LACK OF SUBSTANTIVE PROGRESS, RECOMMENDATIONS I-90-, -9, & -10 ARE CLASSIFIED "OPEN--UNACCEPTABLE RESPONSE."

From: RSPA
To: NTSB
Date: 5/3/1994
Response: BECAUSE OF THE LACK OF AVAILABLE COST INFO IN THIS AREA, RSPA HAS DECIDED TO PUBLISH AN ANPRM RATHER THAN NPRM AS ORIGINALLY PLANNED. RSPA HAS BEGUN DRAFTING THE ANPRM WHICH WILL FOCUS ON HIGH PRESSURE CYLINDERS & SOLICIT INDUSTRY INPUTS ON COSTS, OPERATIONS, & SAFETY BENEFITS.

From: NTSB
To: RSPA
Date: 6/21/1993
Response: OUR RECORDS SHOW THAT WE HAVE NOT RECEIVED ANY FURTHER RESPONSE FROM THE RSPA REGARDING THESE RECOMMENDATIONS. WE WOULD APPRECIATE BEING INFORMED ABOUT EFFORTS THAT HAVE BEEN OR ARE BEING MADE TO IMPLEMENT THESE RECOMMENDATIONS.

From: NTSB
To: RSPA
Date: 12/13/1990
Response:

From: RSPA
To: NTSB
Date: 9/24/1990
Response: A DRAFT NPRM IS BEING DEVELOPED WHICH WILL CONSOLIDATE AND CLARIFY THE SPECIFICATIONS AS WELL AS TESTING AND INSPECTION REQUIREMENTS FOR HIGHT PRESSURE CYLINDERS AS A FOLLOW-ON TO DOCKET HM-181. WE WILL INCLUDE THE ITEMS REQUESTED IN THE RECOMMENDATION AND WILL PLAN IN THE LONG TERM TO FOLLOW-UP THIS ACTION WITH A SIMILAR NPRM ON LOW PRESSURE CYLINDERS. BECAUSE OF THE CONSTRUCTIVE ACTIONS PROPOSED, WE REQUEST THAT RECOMMEDATION I-90-10 BE CLASSIFIED AS "OPEN-ACCEPTABLE ACTION."