Incorrect Lineup Leads to Tugboat Damaging Hylebos Bridge Fender System

9/24/2024

Montlake/Sodo underway in July 2023.

Montlake/Sodo underway in July 2023.(Source: Olympic Tug & Barge Inc.)

​​​WASHINGTON (Sept. 24, 2024) — The deteriorated fender system protecting the Hylebos Bridge in Tacoma, Washington, was damaged beyond repair last October after being struck by a tugboat assisting an articulated tug and barge, or ATB. The National Transportation Safety Board said Tuesday that the captain of the ATB did not line up the vessel correctly to safely transit under the bridge.DCA24FM003.aspx

The tugboat Olympic Scout was assisting the ATB Montlake/Sodo as it transited outbound on the Hylebos Waterway in Tacoma, Washington on Oct. 12, 2023. The Montlake/Sodo’s captain requested the Hylebos Bridge operator open the bridge. While waiting for the Hylebos Bridge to open, the ATB had to pause, and the bow drifted from the center of the channel and moved farther to port (the left side of the channel). The captain steered to starboard, attempting to line up for the bridge, but due to the drag from the Olympic Scout on the port bow, he was unable to move the ATB to starboard.

​The distance between the bow of the Montlake/Sodo and the bridge was 1,276 feet when it began the transit of the waterway, and the channel width between the Hylebos Bridge fenders was 150 feet. The combined breadth of the 78-foot-wide Montlake/Sodo and the 26-foot-wide Olympic Scout was 104 feet, leaving a maximum clearance of 23 feet on either side of the combined unit. 

“Because of the short distance to the bridge and the speed of the ATB, there was insufficient time to correct the lineup before the Olympic Scout struck the fender,” investigators concluded. “Given the slim margin of error for making the bridge transit and the short distance to make the approach, slowing or fully stopping the ATB’s forward motion earlier would have provided the operators more time to correct the lineup and successfully transit through the opening between the bridge’s protective fendering.”


​Damage to Hylebos Bridge fender system following the contact. (Source: U.S. Coast Guard)

The Hylebos Bridge was undamaged following the contact, but the fender system had to be replaced. A marine surveying and consulting firm stated, “the damage caused by the [Olympic Scout contact] resulted in significantly more damage being sustained as would have been, had the fendering structure been of sufficient structural strength.” The bridge fender system’s deteriorated condition contributed to the severity of damage.

Marine Investigation Report 24-26​ is available online.

To report an incident/accident or if you are a public safety agency, please call 1-844-373-9922 or 202-314-6290 to speak to a Watch Officer at the NTSB Response Operations Center (ROC) in Washington, DC (24/7).


​​​​​​